Question: 5

When using change-control processes, which three actions must be considered? (Choose three.)

A. Coordinate scheduling that will be least impactful to production.
B. Coordinate scheduling that works best with the individuals involved.
C. Perform testing in a production environment prior to change-control.
D. Formalize the request based on company policies.
E. Balance troubleshooting needs with productions risks.

Answer: A,D,E